Calculate your OEE — and see which of the three losses is eating it.

Enter one shift's numbers and this free OEE calculator works through the standard calculation steps — availability × performance × quality — showing every intermediate figure, so you can rebuild it in your own sheet. No sign-up, nothing leaves your browser.

Your shift numbers

Inputs

Result

Your OEE

—
enter your numbers
StepFormulaValue

World-class is commonly quoted as 85% for discrete manufacturing; a typical unmeasured plant sits nearer 40–60%. The first measured week is usually lower than everyone expected — that's normal, and it's the point.

Where the number usually lands The benchmarks quoted for OEE only mean something next to each other. World-class for discrete manufacturing is commonly given as 85%, a measured and managed line sits nearer 60%, and a plant measuring for the first time frequently comes in at 40% or below — which is a statement about what was previously invisible rather than about the plant. OEE, PER CENT 0 20 % 40 % 60 % 80 % 100 % World-class, discrete manufacturing ~85 % Measured and managed ~60 % A typical unmeasured plant 40–60 % Common on a first measured week up to 40 % The first measured week is usually lower than everyone expected. That is normal, and it is the point of measuring.
Where the number usually lands 85% world-class, nearer 60% measured and managed, 40% or below on a first week. OEE, PER CENT World-class, discrete manufacturing ~85 % Measured and managed ~60 % A typical unmeasured plant 40–60 % Common on a first measured week up to 40 %
The benchmarks quoted above and in the questions below, on one scale. A first measured week at 40% is a statement about what used to be invisible, not about the plant — which is why the useful comparison is your own line, week on week, after each fix.
Free templates

Downtime tracking sheet & OEE calculation template

Both download as CSV and open straight into Excel, Google Sheets or LibreOffice. The downtime log gives you reason codes worth trending; the OEE sheet contains the same calculation steps as the tool above, one row per shift.

Free to use and adapt. If the manual sheet becomes the bottleneck — someone typing it up every shift, numbers nobody quite trusts — that's the moment automatic machine data collection starts paying for itself.

Frequently asked

OEE calculation questions.

Deeper reading: what an OEE system costs and measuring OEE on an old line.

Four steps. 1) Availability = run time ÷ planned production time, where run time = planned time − unplanned downtime. 2) Performance = (ideal cycle time × total units) ÷ run time. 3) Quality = good units ÷ total units. 4) OEE = availability × performance × quality. The calculator above shows each intermediate value so you can audit it.
85% is the commonly quoted world-class benchmark for discrete manufacturing, 60% is a reasonable "measured and managed" level, and 40% or below is common for plants measuring for the first time. Treat the benchmark loosely — the useful comparison is your own line, week on week, after each fix.
Your ideal cycle time is set too slow — often it's the average rate rather than the design rate. Performance above 100% means the "ideal" isn't ideal; correct it to the design or best demonstrated rate, or speed losses stay invisible.
You can start there — the templates on this page are exactly that. In practice manual sheets decay: entries drift to end-of-shift memory, micro-stops go unrecorded, and the numbers stop being trusted. Once decisions hang on the data, automatic collection (counters, current clamps, PLC reads) is what keeps it honest — that's our OEE management and machine retrofit work.

Want this number on a screen, automatically, every shift?

We instrument the line — old or new, with or without a PLC — and OEE calculates itself from real machine data. Indicatively from ~ZAR 60 000 per line.